A Detailed Explanation
The application of Force Majeure in construction typically hinges on four pillars:
- Externality (the event was not caused by the party)
- Unforeseeability (it could not have been reasonably anticipated)
- Irresistibility (it could not have been avoided or overcome)
- Notice (the party must follow strict contractual protocols to invoke the clause).
When a Force Majeure event occurs, the legal “machinery” of the construction contract changes. Most standard forms, such as AIA A201 or FIDIC Silver Book, distinguish between “Force Majeure” and “Change in Law.” While the outcome—a delay—is the same, the compensation might differ.
It is a common industry standard that Force Majeure provides “Time but no Money.” This means the contractor gets an extension of the completion date but must bear their own costs for idle machinery, overhead, and demobilization. However, if the event persists for an extended period (usually 84 to 180 days), either party may have the right to terminate the contract entirely for convenience.
Origin/Etymology
The phrase originates from the French “force majeure,” meaning “superior force.” It was codified in the Code Napoléon (1804), officially known as the French Civil Code, which significantly influenced civil law systems worldwide.
In English law, the concept was traditionally more rigid under the doctrine of “absolute liability” until the 19th century, when courts began recognizing that “acts of God” or “the King’s enemies” should provide a narrow window of relief. Today, the term is used globally as a standard heading in international construction law.
Example
A contractor is hired to build a skyscraper in a metropolitan area. Mid-project, a massive civil insurrection occurs, leading the government to declare a state of emergency and a mandatory city-wide curfew. Construction crews cannot access the site, and the supply of concrete is cut off. Because the “civil unrest” and “government action” were outside the contractor’s control and were not foreseeable at the time of the bid, the contractor invokes the Force Majeure clause to pause the project timeline without being sued for breach of contract.
Use Cases
- Acts of God: Severe weather (hurricanes, tsunamis), volcanic eruptions, or earthquakes.
- War and Hostilities: Invasions, rebellions, or localized armed conflicts that halt logistics.
- Labor and Supply Chain Shocks: Nationwide “general” strikes or sudden total embargoes on essential materials.
- Regulatory Shifts: Sudden government-mandated site closures (e.g., during a public health emergency).
Benefits & Drawbacks
Benefits:
- Solvency Protection: Prevents contractors from facing ruinous liquidated damages for events they didn’t cause.
- Project Stability: Provides an orderly process for pausing and restarting work rather than immediate litigation.
- Clarity: Defines the boundaries of “acceptable” excuses for non-performance.
Drawbacks:
- Financial Imbalance: Often leaves the contractor paying for “soft costs” (extended insurance, equipment rentals) while the project is stalled.
- Legal Ambiguity: “Foreseeability” is highly subjective and frequently litigated in court.
- Administrative Burden: Failure to provide notice within 24–72 hours can result in the total loss of the right to claim the extension.
Q&A
Does "extraordinary" weather always qualify?
No. If you are building in Florida during hurricane season, a standard storm is “foreseeable.” Only a “100-year storm” or record-breaking event typically qualifies.
Can I claim Force Majeure for a subcontractor's bankruptcy?
Generally, no. A subcontractor’s failure is considered a commercial risk that the prime contractor must manage.
Is Force Majeure the same as "Frustration of Contract"?
No. Frustration occurs when the contract becomes impossible to ever finish; Force Majeure is usually a temporary suspension.
Can an owner invoke Force Majeure?
Yes. For example, if a massive flood destroys the owner’s ability to provide the site or make payments, they may seek relief.
Does Force Majeure cover "Acts of Terrorism"?
Most modern contracts explicitly list terrorism as a Force Majeure event, but it was less common in older templates.
What is a "Catch-all" phrase in these clauses?
It is a phrase like “and any other events beyond the party’s control,” intended to cover events not specifically named.
Does Force Majeure excuse the obligation to pay?
Almost never. While it may excuse the work, it rarely excuses the obligation to pay for work already completed.
How has COVID-19 changed Force Majeure clauses?
Most new contracts now specifically list “pandemics” or “epidemics,” and many have separate clauses for “Public Health Emergencies” to avoid ambiguity.