A Detailed Explanation
Exclusions are categorized by the type of responsibility or cost they remove from the contractor’s obligation. They serve as a critical risk management tool in the bidding phase.
The three primary categories of Exclusions are:
- Scope Exclusions (Work Tasks): These remove specific physical work activities from the contract. Examples include: Excavation contractor excludes dewatering activities; Interior finishes contractor excludes custom millwork; GC excludes connection to public utilities.
- Cost Exclusions (Financial Items): These remove financial liabilities or items from the lump-sum price. Examples include: The bid price excludes all permit and inspection fees; The bid excludes sales tax or Value Added Tax (VAT); Price excludes any cost escalation beyond 90 days.
- Risk/Liability Exclusions (Conditions): These remove responsibility for specific site conditions or external events. Examples include: Subcontractor excludes liability for damage to existing utilities not marked; GC excludes responsibility for unforeseen geotechnical conditions (e.g., rock); The contract excludes any liquidated damages for owner-caused delays.
The best practice for listing exclusions is to be hyper-specific, particularly by referencing the relevant section of the contract documents or specifications being excluded. A vague exclusion, such as “Excludes all costs,” is generally unenforceable, while a specific exclusion, such as “Excludes costs associated with the installation of Owner Furnished Equipment (OFE) per Section 23 00 00,” is legally defensible.
Origin/Etymology
The concept of explicitly defining what is not included predates formalized construction contracts and is rooted in the early legal tradition of contract law and risk definition. In common law, contractual ambiguity is often resolved against the party who drafted the document (the doctrine of contra proferentem). This principle created a strong incentive for contractors and insurance underwriters to become meticulously detailed in what they agreed to cover.
The modern practice of using a dedicated “Exclusions” list in a bid or proposal gained prominence as construction projects became more fragmented and complex, relying on multiple specialized subcontractors. Beginning in the mid-20th century, standard industry contract forms (such as those from the American Institute of Architects, AIA) emphasized the need for clear scope definition, thereby formalizing the complementary role of the exclusions list.
Example
A roofing contractor is submitting a bid to replace the roof on a commercial building for a General Contractor (GC).
- Scope Included: Tear-off of existing single-ply membrane, installation of new insulation board, and installation of new TPO roof membrane.
- Exclusions List: The contractor includes the following critical exclusions in their proposal:
- Structural: Excludes any structural repairs to the existing decking, trusses, or framing found underneath the existing membrane. (If wood rot is found, this is a change order.)
- Perimeter: Excludes replacement or repair of interior drywall, paint, or exterior cornice trim damaged during the tear-off process. (Transferring interior finish risk to another trade or the GC).
- Hazardous Materials: Excludes the testing for or abatement of any asbestos or lead-containing materials discovered in the existing roof system or surrounding walls.
- Permitting: Excludes all fees and responsibilities related to obtaining local municipal building permits for the work.
If the GC accepts the bid without amending the exclusions, the roofing contractor is not responsible for any of the excluded items or costs.
Use Cases
Exclusions are indispensable risk control mechanisms used across the project lifecycle:
- Contractual Scope Definition (Bidding): They are primarily used during the bidding phase to precisely draw the line around the submitted price. Clear exclusions allow the contractor to submit a tighter, more competitive bid because they don’t need to pad their price with contingencies for tasks they don’t intend to perform.
- Subcontractor Risk Management: General Contractors use flow-down clauses to pass on specific responsibilities to subcontractors. Simultaneously, they require subcontractors to clearly list their exclusions to prevent critical scope gaps. The GC then uses bid leveling software to identify and cover these gaps (i.e., making sure an excluded task is included in another bid).
- Negotiation Tool: During contract negotiation, the list of exclusions often becomes a key point of discussion. The owner may challenge an exclusion (e.g., “We need you to include the permit fees”), forcing the contractor to either remove the exclusion and adjust the price upward or maintain the exclusion.
- Dispute Resolution: In the event of a contractual dispute or a claim for a change order, the exclusions list is the first document reviewed. It provides definitive proof that a contested task or cost was intentionally left out of the original agreement, serving as the contractor’s primary defense against performing disputed work at their expense.
Benefits & Drawbacks
Benefits:
- Clear Liability Boundary: Provides an explicit, legally defensible line between the contractor’s responsibility and the owner’s or other trade’s responsibility.
- Competitive Pricing: Allows the contractor to reduce contingency for unwanted work, leading to a leaner, more competitive base bid price for the owner.
- Avoids Costly Surprises: Protects the contractor’s profit margin from being eroded by having to absorb costs for tasks they never intended to include.
Drawbacks:
- Scope Gaps and Delays: Inadequately detailed exclusions can create unassigned work (scope gaps). When these gaps are discovered on-site, it results in costly delays and unavoidable change orders.
- Client Perception: A proposal with an overly long, dense, or aggressively worded list of exclusions can make a contractor appear litigious or uncooperative, negatively impacting the client relationship.
- Contractual Ambiguity: Vague or overly broad exclusions (e.g., “Excludes all temporary items”) are often deemed unenforceable because they lack the required specificity to define the scope limit.
Q&A
What is the main legal purpose of an Exclusion?
The main legal purpose is to prevent contractual ambiguity. By explicitly defining what is not included, the contractor avoids the legal doctrine where unstated necessary work is assumed to be part of the general contract scope.
What is the risk to a contractor who fails to list a necessary Exclusion in a fixed-price bid?
The contractor risks having to perform the omitted work at their own expense, as the owner may argue that the unstated but necessary work was implicitly included in the lump-sum price.
What is the difference between a scope gap and a scope overlap in relation to Exclusions?
A scope gap occurs when a necessary task is excluded by all trades, meaning no one is responsible. A scope overlap occurs when a task is included by multiple trades, leading to duplicate billing or confusion over who performs the work. Exclusions help minimize both.
In which section of a bid or contract should Exclusions be clearly placed?
Exclusions should be placed in a dedicated, clearly titled section immediately following the price and the detailed scope of work. They should not be buried in general conditions or fine print.
What is the meaning of "OFE" in a list of Exclusions?
“OFE” stands for Owner Furnished Equipment. An exclusion for OFE installation means the contractor will build the space but will not install specific equipment (e.g., specialized medical devices, data racks) that the owner purchases directly.
What is the best practice for a contractor to make an Exclusion legally defensible?
The best practice is to make the exclusion specific and referential. For example, instead of saying “Excludes painting,” state: “Excludes all finish painting on interior surfaces per Section 09 90 00.”
How does a General Contractor use Exclusions during the bid leveling process?
The GC compares the exclusions lists of all competing subcontractor bids to the project’s overall scope. This process highlights scope gaps created by the subcontractors’ exclusions, allowing the GC to ensure these items are covered elsewhere or priced back into the final contract.
Provide an example of a financial Exclusion that might appear in a bid.
A common financial exclusion is: “This price excludes all fees associated with mandatory municipal permit applications and local impact fees.” This places the financial risk of fluctuating government fees back onto the owner.